Thursday:
garbage hauled out.remaining material left on site.
water sealed topping compound left on site for texture.
final skim coat
Deck functionally complete.
Wednesday:
Will be at Dubinets this morning to wrap up loose ends, and will head over to Holbrook after lunch.
Job restart:
requesting 20 feet of Fascia for the front of the deck, 1 box of topping compound, and one clean 5 gallon plastic bucket .
Thursday:
Wednesday:
Passed inspection, insulated, drywalled, first taped tight.
Was not able to make it to Holbrook and finish what I needed to do at Dubinets. Want permission to start my day Thursday at Holbrook for Toilet installation.
143 carriage bolts-
143 nuts-
33 lag bolts-
319 washers-
All installed & ready to call for an inspection.
Biggest problem was no single HD had enough hardware to complete the entire project. Michael and I bought as much as each store had on hand to keep the job going, but had to make multiple trips to restock.
This is the bolt pattern being used.
Request undelivered washers, 30 3" lag bolts with 30 washers, 3 garbage bags & 1 box of t50 1/2" staples.
If you allow me to sister the joists for cleaner blocking between the garage & 2nd story wall plates, we would need 8- 2"X 8"X 8' PT boards.
No washers guys...
An example of sistered joists @ the nearest end.
Removed the remaining insulation.
Jammed insulation into the bays behind the tar paper.